2024 Butler Road Project Schedule

The 2024 Butler Road and Water Main Replacement Project is slated to begin July 1st, 2024 and end in early September of 2024. Below, the Village has provided residents a preliminary schedule of different phases of the project. Please remember that these dates are preliminary and subject to change depending on weather conditions and other factors. Updates to this schedule will be posted as the project moves along.

Preliminary Schedule:
Task Name Duration Start Date Finish Date
Water Main and Adjustments 26 days total 7/1/2024 8/5/2024
Traffic Control 1 day 7/1/2024 7/1/2024
Saw Cutting 1 day 7/1/2024 7/1/2024
Water Main Work 21 days 7/8/2024 8/5/2024
Paving Program 21 days 8/7/2024 9/4/2024
Concrete Removals 3 days 8/7/2024 8/9/2024
Curb and Gutter 4 days 8/8/2024 8/13/2024
Sidewalks 5 days 8/13/2024 8/19/2024
Concrete Driveways/Pavement 1 day 8/19/2024 8/19/2024
Restoration 3 days 8/20/2024 8/22/2024
Milling 1 day 8/23/2024 8/23/2024
EBS 2 days 8/26/2024 8/27/2024
Grading 2 days 8/26/2024 8/27/2024
Binder 1 day 8/31/2024 8/31/2024
Surface 1 day 9/2/2024 9/2/2024
Line Painting 1 day 9/4/2024 9/4/2024